Resurfacing – at last!
Ayrshire Roads Alliance have notified the Community Council that they will resurface the south road into Dunure in two stages:
- 6th-20th July: from the harbour to the Coastal Path corner
- 20th July to 3rd August: Coastal Path corner to Dunure Mains and the main road.
We don’t yet know about what will happen to the chicanes on the road, which need to be re-located with a revised layout.
Thanks go to the Community Council for their sustained pressure and to Provost Iain Campbell for his support.
The intention is to have the works completed before the Festival of the Sea which takes place on Saturday 15th August, starting at 1:00 pm.
Watch this space for details on traffic flow and parking arrangements.